Key Highlights:
- Senior supervision of works on the Abbotts Road intersection during a 30-day occupation period
- Constructing a new 3-span Super-T bridge with reinforced earth wall approaches and a duplicated 2km roadway
- Relocating vital public utilities and mitigating flood risks with advanced drainage solutions
- Constructing new walking and cycling paths
- Modification of intersections
Scope of work
- Excavation
- Installation of traffic signals and shared user paths
- Structural modifications and strengthening
- Drainage upgrades and kerb/channel construction
- Major asset relocation and water main works
- Working around live assets
- Safe access maintenance for surrounding businesses